Subzero Temps in the Oilfield

130 CY of Concrete In Subzero Temperatures

CCI was asked in Early November to install an Oilfield freshwater Depot. The project consisted of Moving 15,000 CY of dirt, fill, and gravel and pouring 125 CY of concrete in subzero temperatures. CCI worked around the clock to move dirt and fill as quickly as possible to stay ahead of frost.  Installation was finished in late January 2014.